Thursday, December 12, 2024
HomeNewsFarsley: Calverley Lane to close for road maintenance works

Farsley: Calverley Lane to close for road maintenance works

The next stage of roadworks through Farsley will start on Calverley Lane, between Bagley Lane and Lees Lane, later this month.

Work is due to start on Monday, 18 February for three weeks. Two weeks will be to carry out footway repairs, followed by one week of carriageway resurfacing.

The footway works can be carried out on temporary lights to maintain access. The resurfacing works however will need to be carried out under a road closure.

ALl work will take place outside of peak traffic times, Monday to Friday between 9.30am–3.30pm.

Last month Farsley Town Street was closed during daytime hours for over a week to allow for maintenance work to be carried out.

____________

We encourage anyone living or working in West Leeds to use this website to tell their news. You can either use our Create an Article page, or e-mail us at news@westleedsdispatch.com.



LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Recent Posts

Stay Connected

3,172FansLike
518FollowersFollow
3,859FollowersFollow